Assessing risk dimensions in dry port projects: prioritization, interdependence and heterogeneity
  Purpose
We identify and further aggregate the most commonly engaged risk factors in dry port projects into dimensions. Noting the importance of developing a multi-perspective view of risk, we further assess the priority, interdependency and heterogeneity of the identified risk dimensions.

Design/methodology/approach
We identified 44 risk factors from the literature, which were aggregated via exploratory factor analysis (EFA) into 8 major risk dimensions. We employ a fuzzy-based decision-making trial and evaluation laboratory (DEMATEL) relationship map to articulate various relationships among the risk dimensions.

Findings
“Cost” emerged as the most important risk influencing the success of the dry port project, followed by “location,” “accessibility,” “infrastructural” and “operational,” which were also ranked prominently.

Originality/value
This study offers significant insight into the management of risk in dry port projects. By aggregating key risk factors into distinct dimensions, we develop a structured framework for effective risk assessment and management. The insights gleaned from the study extend globally, as it serves as a concrete knowledge base to understand potential barriers to successful dry port projects.

  • Date:

    16 July 2024

  • Publication Status:

    Published

  • Publisher

    Emerald Publishing Limited

  • DOI:

    10.1108/MABR-09-2023-0064

  • ISSN:

    2397-3757

  • Funders:

    Edinburgh Napier Funded

Citation

Rodrigues, T. D. A., Ojiako, U., Mota, C. M. D. M., Marshall, A., Chipulu, M., & Dweiri, F. (2024). Assessing risk dimensions in dry port projects: prioritization, interdependence and heterogeneity. Maritime Business Review, 9(4), 311-330. https://doi.org/10.1108/MABR-09-2023-0064

Authors

Keywords

Dry port projects, Risk identification, Priority, Interdependencies, Heterogeneity, Multistakeholder perspective